Criteria Page of the Replan Wizard

Use this page to select which code of the project you want to replan.

Contents

Field Description
Criteria Use the drop-down list to select one of the following options:
  • Total Project
  • Control Account
  • Work Package
  • WBS
  • OBS
  • WP
  • Control Account.Location
  • Work Package.Charge Number
  • CAM
  • Work Package Manager
If the code you selected has a hierarchical structure, the Replan process includes that code and its children if the Include all children option is selected.
Selection This field is available only if you selected a criterion other than Total Project in the Criteria field. Click to display the Code Lookup dialog box, where you can select the code that you want to include in the replan. For example, if you selected Control Account in the Criteria field, the Code lookup dialog box displays all control accounts for the selected project.
Include all children This check box is available if you selected a code validated with a code file in the Selection field. Selecting this check box instructs Cobra to run the replan process against any code assignments with the selected code and its children. For example, if you selected WBS code 1.1 in the Selection field and you selected the Include all children option, the replan process will include control accounts and/or work packages with code assignments of 1.1 or any child codes, such as 1.1.1 and 1.1.2.